  • Upgrade of the bottom loading skid on a turnkey project at Rades HCL terminal, including :
    • Preliminary engineering.
    • Detailed engineering in Automation, E&I and Process.
    • Supply of equipment (Cables, cables trays, junction box…).
    • Integration and configuration of the batch controllers.
    • Mechanical and electrical assembly and installation.
    • Supervision of ancillary works.
    • Calibration of flowmeters through the batch controllers.
    • FAT.
    • Pre-commissioning, commissioning and start-up.